Which of the following disaster recovery tests is the most intrusive to business operations?
A.
Parallel
B.
Simulation
C.
Full-interruption
D.
Checklist
Explanation:
Full-interruption tests require the original site to be completely
shut down and all processes moved to an alternate site. This can be very disruptive
to a company, but is the only way to really know the disaster recovery plan will
work when it is needed.