which one?

Part of your change management plan details what should happen in the change control system
for your project. Theresa, a junior project manager, asks what the configuration management
activities are for scope changes. You tell her that all of the following are valid configuration
management activities except for which one?

Part of your change management plan details what should happen in the change control system
for your project. Theresa, a junior project manager, asks what the configuration management
activities are for scope changes. You tell her that all of the following are valid configuration
management activities except for which one?

A.
Configuration Identification

B.
Configuration Verification and Auditing

C.
Configuration Status Accounting

D.
Configuration Item Costing

Explanation:
Configuration item cost is not a valid activity for configuration management. Cost
changes are managed by the cost change control system; configuration management is
concerned with changes to the features and functions of the project deliverables.