You and your project team have identified the project risks and now are analyzing the probability
and impact of the risks. What type of analysis of the risks provides a quick and high-level review of
each identified risk event?
A.
Quantitative risk analysis
B.
Qualitative risk analysis
C.
Seven risk responses
D.
A risk probability-impact matrix
Explanation:
Qualitative risk analysis is a high-level, fast review of the risk event. Qualitative risk
analysis qualifies the risk events for additional analysis.