Which of the following activities are performed by the ‘Do’ cycle component of PDCA (plan-do-check-act)? Each correct answer represents a complete solution. Choose all that apply.
A.
It detects and responds to incidents properly.
B.
It determines controls and their objectives.
C.
It manages resources that are required to achieve a goal.
D.
It performs security awareness training.
E.
It operates the selected controls.
Explanation:
The ‘Do’ cycle component performs the following activities: It operates the selected
controls. It detects and responds to incidents properly. It performs security awareness training. It
performed by the ‘Plan’ cycle component of PDCA.