What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

What project management plan is most likely to direct the quantitative risk analysis process for a
project in a matrix environment?

What project management plan is most likely to direct the quantitative risk analysis process for a
project in a matrix environment?

A.
Risk analysis plan

B.
Staffing management plan

C.
Risk management plan

D.
Human resource management plan

Explanation:
The risk management plan defines how risks will be identified, analyzed, responded
incorrect. The human resources management plan does define how risks will be analyzed.