What are the process activities of this phase?

The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully
integrated system for certification testing and accreditation. What are the process activities of this
phase? Each correct answer represents a complete solution. Choose all that apply.

The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully
integrated system for certification testing and accreditation. What are the process activities of this
phase? Each correct answer represents a complete solution. Choose all that apply.

A.
Certification analysis

B.
Assessment of the Analysis Results

C.
Configuring refinement of the SSAA

D.
System development

E.
Registration

Explanation:
The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to
obtain a fully integrated system for certification testing and accreditation. This phase takes place
between the signing of the initial version of the SSAA and the formal accreditation of the system.
This phase verifies security requirements during system development. The process activities of
this phase are as follows: Configuring refinement of the SSAA System development Certification
activity.