In which of the following types of tests are the disaster recovery checklists distributed to the members
of disaster recovery team and asked to review the assigned checklist?
A.
Parallel test
B.
Simulation test
C.
Full-interruption test
D.
Checklist test
Explanation:
A checklist test is a test in which the disaster recovery checklists are distributed to the
members of the disaster recovery team. All members
are asked to review the assigned checklist. The checklist test is a simple test and it is easy to conduct
this test. It allows to accomplish the
following three goals:
It ensures that the employees are aware of their responsibilities and they have the refreshed
knowledge.
It provides an individual with an opportunity to review the checklists for obsolete information and
update any items that require
modification during the changes in the organization.
It ensures that the assigned members of disaster recovery team are still working for the
organization.
Answer option B is incorrect. A simulation test is a method used to test the disaster recovery plans. It
operates just like a structured walkthrough test. In the simulation test, the members of a disaster recovery team present with a disaster
scenario and then, discuss on
appropriate responses. These suggested responses are measured and some of them are taken by the
team. The range of the simulation test
should be defined carefully for avoiding excessive disruption of normal business activities.
Answer option A is incorrect. A parallel test includes the next level in the testing procedure, and
relocates the employees to an alternate
recovery site and implements site activation procedures. These employees present with their
disaster recovery responsibilities as they would
for an actual disaster. The disaster recovery sites have full responsibilities to conduct the day-to-day
organization’s business.
Answer option C is incorrect. A full-interruption test includes the operations that shut down at the
primary site and are shifted to the recovery
site according to the disaster recovery plan. It operates just like a parallel test. The full-interruption
test is very expensive and difficult to
arrange. Sometimes, it causes a major disruption of operations if the test fails.