Which of the following recovery plans includes specific strategies and actions to deal with specific
variances to assumptions resulting in a particular security problem, emergency, or state of affairs?
A.
Business continuity plan
B.
Disaster recovery plan
C.
Continuity of Operations Plan
D.
Contingency plan
Explanation:
A contingency plan is a plan devised for a specific situation when things could go wrong. Contingency
plans include specific strategies and actions to deal with specific variances to assumptions resulting
in a particular problem, emergency, or state of affairs. They also include a monitoring process and
triggers for initiating planned actions.
Answer option B is incorrect. Disaster recovery is the process, policies, and procedures related to
preparing for recovery or continuation of technology infrastructure critical to an organization after a
natural or human-induced disaster.
Answer option A is incorrect. It deals with the plans and procedures that identify and prioritize the
critical business functions that must be preserved.
Answer option C is incorrect. It includes the plans and procedures documented that ensure the
continuity of critical operations during any period where normal operations are impossible.