Which of the following processes is described in the statement below?

Which of the following processes is described in the statement below?
“It is the process of implementing risk response plans, tracking identified risks, monitoring residual
risk, identifying new risks, and evaluating risk process effectiveness throughout the project.”

Which of the following processes is described in the statement below?
“It is the process of implementing risk response plans, tracking identified risks, monitoring residual
risk, identifying new risks, and evaluating risk process effectiveness throughout the project.”

A.
Monitor and Control Risks

B.
Identify Risks

C.
Perform Qualitative Risk Analysis

D.
Perform Quantitative Risk Analysis

Explanation:
Monitor and Control Risk is the process of implementing risk response plans, tracking identified risks,
monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout
the project. It can involve choosing alternative strategies, executing a contingency or fallback plan,
taking corrective action, and modifying the project management plan.

Answer option C is incorrect. This is the process of prioritizing risks for further analysis or action by
accessing and combining their probability of occurrence and impact.
Answer option B is incorrect. This is the process of determining which risks may affect the project
and documenting their characteristics.
Answer option D is incorrect. This is the process of numerically analyzing the effect of identified risks
on overall project objectives.
“A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth