What component of the change management system is responsible for evaluating, testing, and
documenting changes created to the project scope?
A.
Scope Verification
B.
Project Management Information System
C.
Integrated Change Control
D.
Configuration Management System
Explanation:
The change management system is comprised of several components that guide the change request
through the process. When a change request is made that will affect the project scope. The
Configuration Management System evaluates the change request and documents the features and
functions of the change on the project scope.