which one?

Part of your change management plan details what should happen in the change control system for
your project. Theresa, a junior project manager, asks what the configuration management activities
are for scope changes. You tell her that all of the following are valid configuration management
activities except for which one?

Part of your change management plan details what should happen in the change control system for
your project. Theresa, a junior project manager, asks what the configuration management activities
are for scope changes. You tell her that all of the following are valid configuration management
activities except for which one?

A.
Configuration Verification and Auditing

B.
Configuration Item Costing

C.
Configuration Identification

D.
Configuration Status Accounting

Explanation:
Configuration item cost is not a valid activity for configuration management. Cost changes are
managed by the cost change control system; configuration management is concerned with changes
to the features and functions of the project deliverables.



Leave a Reply 0

Your email address will not be published. Required fields are marked *