Which of the following documents is described in the statement below?
“It is developed along with all processes of the risk management. It contains the results of the
qualitative risk analysis, quantitative risk analysis, and risk response planning.”
A.
Risk register
B.
Risk management plan
C.
Quality management plan
D.
Project charter
Explanation:
Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk
analysis, and risk response planning.
Description, category, cause, probability of occurring, impact on objectives, proposed responses,
owner, and the current status of all identified risks are put in the risk register. Risk register is
developed along with all processes of the risk management from Plan Risk Management
through Monitor and Control Risks.
Answer option C is incorrect. The quality management plan is a component of the project
management plan. It describes how the project team will implement the organization’s quality
policy. The quality management plan addresses quality control (QC), quality assurance (QA), and
continuous process improvement for the project. Based on the requirement of the project, the
quality management plan may be formal or informal, highly detailed or broadly framed.
Answer option B is incorrect. Risk management plan includes roles and responsibilities, risk analysis
definitions, timing for reviews, and risk threshold. The Plan Risk Responses process takes input from
risk management plan and risk register to define the risk response.
Answer option D is incorrect. The project charter is the document that formally authorizes a project.
The project charter provides the project manager with the authority to apply organizational
resources to project activities.