Which of the following baselines identifies the specifications required by the resource that meet
the approved requirements?
A.
Functional baseline
B.
Allocated baseline
C.
Product baseline
D.
Developmental baseline
Explanation:
Allocated baseline identifies the specifications that meet the approved requirements.
Answer A is incorrect. Functional baseline identifies the initial specifications before any changes
are made.
Answer C is incorrect. Product baseline identifies the minimal specification required by the
resource to meet business outcomes.
Answer D is incorrect. Developmental baseline identifies the state of the resources as it is
developed to meet or exceed expectations and requirements.