HOTSPOT
A company maintains separate environments for development, test, and production. The
company uses the project deployment model for SQL Server Integration Services (SSIS)
deployments.
You create an SSIS project to perform a daily refresh of the data warehouse and data
models. The project has five packages.
You need to configure the project to ensure that the development, test, and production
teams can run each package without manually adding server-specific information.
Which program should you use?
To answer, select the appropriate program in the answer area.
Explanation: