Which of the following documents is described in the statement below?
“It is developed along with all processes of the risk management. It contains the results of the
qualitative risk analysis, quantitative risk analysis, and risk response planning.”
A.
Quality management plan
B.
Risk management plan
C.
Risk register
D.
Project charter
Explanation:
Risk register is a document that contains the results of the qualitative risk analysis, quantitative
risk analysis, and risk response planning.
Risk register is developed along with all processes of the risk management from Plan Risk
Management through Monitor and Control Risks.
Answer A is incorrect. The quality management plan is a component of the project management
plan. It describes how the project team will implement the organization’s quality policy. The quality
management plan addresses quality control (QC), quality assurance (QA), and continuous
process improvement for the project. Based on the requirement of the project, the quality
management plan may be formal or informal, highly detailed or broadly framed.
Answer B is incorrect. Risk management plan includes roles and responsibilities, risk analysis
definitions, timing for reviews, and risk threshold. The Plan Risk Responses process takes input
from risk management plan and risk register to define the risk response.Answer D is incorrect. The project charter is the document that formally authorizes a project. The
project charter provides the project manager with the authority to apply organizational resources to
project activities.