Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

Which of the following components ensures that risks are examined for all new proposed change
requests in the change control system?

Which of the following components ensures that risks are examined for all new proposed change
requests in the change control system?

A.
Configuration management

B.
Scope change control

C.
Risk monitoring and control

D.
Integrated change control

Explanation:

Integrated change control is the component that is responsible for reviewing all aspects of a
change’s impact on a project – including risks that may be introduced by the new change.
Integrated change control is a way to manage the changes incurred during a project. It is a method
that manages reviewing the suggestions for changes and utilizing the tools and techniques to
evaluate whether the change should be approved or rejected. Integrated change control is a
primary component of the project’s change control system that examines the affect of a proposed
change on the entire project.
Answer A is incorrect. Configuration management controls and documents changes to the
features and functions of the product scope.
Answer B is incorrect. Scope change control focuses on the processes to allow changes to enter
the project scope.
Answer C is incorrect. Risk monitoring and control is not part of the change control system, so this
choice is not valid.



Leave a Reply 0

Your email address will not be published. Required fields are marked *