You are the project manager for BlueWell Inc. Your current project is a high priority and high
profile project within your organization. You want to identify the project stakeholders that will have
the most power in relation to their interest on your project. This will help you plan for project risks,
stakeholder management, and ongoing communication with the key stakeholders in your project.
In this process of stakeholder analysis, what type of a grid or model should you create based on
these conditions?
A.
Stakeholder power/interest grid
B.
Stakeholder register
C.
Influence/impact grid
D.
Salience model
Explanation:
The power/interest grid groups stakeholders based on their level of authority (power) and their
level of interest in your project. The power/interest grid forms a group of the stakeholders based
on their level of authority (power) and their level of interest in the project.
Interest accounts to what degree the stakeholders are affected by examining the project or policy
change, and to what degree of interest or concern they have about it. Power accounts for the
influence the stakeholders have over the project or policy, and to what degree they can help to
accomplish, or block, the preferred change.
Stakeholders, who have high power and interests associated with the project, are the people or
organizations that are fully engaged with the project. When trying to generate strategic change,
this community is the target of any operation.
Answer B is incorrect. The stakeholder register is a listing of stakeholder information and
communication requirements.
Answer D is incorrect. The salience model groups the stakeholders based on their power,
urgency, and legitimacy in the project.
Answer C is incorrect. The influence/impact grid charts is based on the stakeholders involvement
and ability to effect changes to the project’s planning and execution.