You create a new application in PerformancePoint Planning Server. You create a calendar for the application. Your manager wants another calendar for the manufacturing department. The department uses different fiscal year dates. You need to create the new calendar. What should you do first?
A.
Create a new dimension.
B.
Create a new application.
C.
Create a new business rule.
D.
Create a new model subsite.