You need to modify the project to reflect this temporary change

You are managing a project schedule in Microsoft Office Project Standard 2007. Two resources are changing from the day shift to the night shift for 2 weeks. You need to modify the project to reflect this temporary change. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. Two resources are changing from the day shift to the night shift for 2 weeks. You need to modify the project to reflect this temporary change. What should you do?

A.
Set the Night Shift calendar as the project calendar.

B.
Apply the Night Shift calendar to each resource’s calendar.

C.
Add a Night Shift entry to the exceptions of the project calendar, with the appropriate dates and hours set for these 2 weeks.

D.
Add a Night Shift entry to the exceptions of each resource’s calendar, with the appropriate dates and hours set for these 2 weeks.