What should you do?

You work from 8:00 A M. to 4:00 P.M. When scheduling projects in Microsoft Office Project Standard 2007, you set the working time of the project accordingly. When you create a new task, Project shows the finish time as 9:00 A M. on the following day. You need the finish time of new tasks to default to 4:00 P.M. What should you do?

You work from 8:00 A M. to 4:00 P.M. When scheduling projects in Microsoft Office Project Standard 2007, you set the working time of the project accordingly. When you create a new task, Project shows the finish time as 9:00 A M. on the following day. You need the finish time of new tasks to default to 4:00 P.M. What should you do?

A.
Modify the default task duration.

B.
Enter 4:00 P.M. as the finish time.

C.
Decrease the default hours per day by one hour.

D.
Change the default end time from 5:00 P.M. to 4:00 P.M.



Leave a Reply 0

Your email address will not be published. Required fields are marked *