You plan the next phase of a project in more detail by creating new tasks in an existing project plan. You insert a new task between two existing tasks. Microsoft Office Project Standard 2007 automatically creates a predecessor and successor. You need to disable the automatic creation of predecessors and successors. What should you do?
A.
Turn off the autolink option.
B.
Calculate multiple critical paths.
C.
Delete links that you do not need.
D.
Enable the manual calculation mode.