You are tracking a road construction project in Microsoft Office Project Standard 2007. The Earned Value is based on the number of kilometers of road you build. You need to track and update your progress. Which attribute should you use?
A.
CV%
B.
SV%
C.
% Complete
D.
Physical % Complete