you need to know whether the actual cost exceeds the budget

You are tracking a project in Microsoft Office Project Standard 2007. For the work performed to date, you need to know whether the actual cost exceeds the budget. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. For the work performed to date, you need to know whether the actual cost exceeds the budget. What should you do?

A.
Set the status date to the beginning of the project, and then establish whether the earned value cost variance (CV) is negative.

B.
Set the status date to the last status update deadline, and then compare the estimate at completion (EAC) to the budgeted cost of work scheduled (BCWS).

C.
Set the status date to the end of the project, and then compare the actual cost of work performed (ACWP) to the budgeted cost of work scheduled (BCWS).

D.
Set the status date to the last status update deadline, and then compare the actual cost of work performed (ACWP) to the budgeted cost of work scheduled (BCWS).