Your company tracks work effort. In Microsoft Office Project Standard 2007, you have created a custom field named Text1 to capture resource departments. You are displaying the project in the Resource Sheet view. The Work table is displayed. You need to be able to quickly view scheduled work hours for all departments, by department. What should you do?
A.
Create a filter to display resources by selected departments, and then apply the new filter to the current view.
B.
Create a group to display resources grouped by the Type field, and then apply the new group to the current view.
C.
Create a group to display resources grouped by the Text1 field, and then apply the new group to the current view.
D.
Activate the autofilter option, and then in the list for the Text1 field, select the departments you need to view.