In Microsoft Office Project Standard 2007, you are tracking a project by duration. The Updating task status updates resource status option is not activated. You need to display the current status of the project. What should you display?
A.
The % Work Complete field in the Project Statistics dialog box.
B.
The % W. Complete field for the project summary task in the task Work table.
C.
The % Complete field for the project summary task in the task Tracking table.
D.
The Physical % Comp. field for the project summary task in the task Tracking table.