You are building a schedule for an upcoming project in Microsoft Office Project Standard 2007. You must report the potential schedule variance to the stakeholders before they will approve the project. You need to estimate the potential variance before you set a baseline. What should you do?
A.
Calculate variance by leveling resources.
B.
Calculate schedule by using PERT analysis.
C.
Calculate variance by using the Start Variance and Finish Variance fields.
D.
Calculate a new estimate at completion (EAC) based on the schedule performance index (SPI) and cost performance index (CPI).