You need to set up your project plan so that you can start tracking the costs

You are using Microsoft Office Project Professional 2007 to plan a project. The project has a fixed budget. You will use the budget-tracking feature to track the project costs against the budget. You need to set up your project plan so that you can start tracking the costs. What should you do first?

You are using Microsoft Office Project Professional 2007 to plan a project. The project has a fixed budget. You will use the budget-tracking feature to track the project costs against the budget. You need to set up your project plan so that you can start tracking the costs. What should you do first?

A.
Save a project baseline.

B.
Create budget resources.

C.
Display the Earned Value Cost Indicators table.

D.
Assign cost resources to the project summary task.



Leave a Reply 0

Your email address will not be published. Required fields are marked *