You need to keep track of how close the forecast completion dates of these deliverables are to their target dates

Project team members are working on several of the tasks in your Microsoft Office Project Standard 2007 schedule in parallel. Each is of these tasks is represented by a summary task and a series of linked subtasks. You need to keep track of how close the forecast completion dates of these deliverables are to their target dates. What should you do?

Project team members are working on several of the tasks in your Microsoft Office Project Standard 2007 schedule in parallel. Each is of these tasks is represented by a summary task and a series of linked subtasks. You need to keep track of how close the forecast completion dates of these deliverables are to their target dates. What should you do?

A.
Flag the summary tasks as milestones.

B.
Set a deadline on the last subtask of each deliverable.

C.
Convert the summary tasks into milestones by setting the duration of each to 0.

D.
Ensure that the earned value is calculated based on physical percentage of completion.