You are creating a schedule in Microsoft Office Project Standard 2007. Task A starts before Task B, but is dependent on the schedule of Task B. You need to model the dependency between the tasks without lead or lag time. What should you do?
A.
Create a start-to-start dependency from Task A to Task B.
B.
Create a finish-to-start dependency from Task A to Task B.
C.
Create a start-to-finish dependency from Task B to Task A.
D.
Create a finish-to-start dependency from Task B to Task A.