Which view should you use?

You are assigning resources to a project in Microsoft Office Project Standard 2007. You allocate generic resources to a task and apply a work contour to some of the assignments. You need to view the assignments to verify that the work has been distributed correctly. Which view should you use?

You are assigning resources to a project in Microsoft Office Project Standard 2007. You allocate generic resources to a task and apply a work contour to some of the assignments. You need to view the assignments to verify that the work has been distributed correctly. Which view should you use?

A.
Network Diagram

B.
Resource Graph

C.
Resource Sheet

D.
Task Usage