You need to allocate the remaining work to Resource B without removing or changing the Actual Work already recorded for Resource A

You are tracking a project in Microsoft Office Project Standard 2007. Resource A has reported Actual Work performed on a task. Resource A is changing job roles. Resource B will complete the task. You need to allocate the remaining work to Resource B without removing or changing the Actual Work already recorded for Resource A . What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. Resource A has reported Actual Work performed on a task. Resource A is changing job roles. Resource B will complete the task. You need to allocate the remaining work to Resource B without removing or changing the Actual Work already recorded for Resource A . What should you do?

A.
In the Resource Sheet view, replace Resource As name with that of Resource B

B.
In the Gantt Chart view, replace Resource As name in the Resource Names field with that of Resource B.

C.
In the Assign Resources dialog box, for each task that currently utilizes Resource A, replace Resource A with Resource B.

D.
In the Assign Resources dialog box, for each task that currently utilizes Resource A, delete Resource A and assign Resource B.