You need to create a task that reflects the resource restrictions so that you can efficiently track the estimates to completion

You are tracking a project in Microsoft Office Project Standard 2007. A resource can commit 2 hours of each 8-hour day to a task but cannot accurately estimate how long it will take him to complete the task. While working on the task, the resource will be better able to predict a completion date. You need to create a task that reflects the resource restrictions so that you can efficiently track the estimates to completion. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. A resource can commit 2 hours of each 8-hour day to a task but cannot accurately estimate how long it will take him to complete the task. While working on the task, the resource will be better able to predict a completion date. You need to create a task that reflects the resource restrictions so that you can efficiently track the estimates to completion. What should you do?

A.
Create a fixed units task, and then assign the resource to the task at 25%.

B.
Create a fixed units task, and then assign the resource to the task at 100%.

C.
Create a fixed duration task, and then assign the resource to the task at 25%.

D.
Create a fixed duration task, and then assign the resource to the task at 100%.