You need to configure Project so that you can independently record the actual work and the actual duration

You are tracking a project in Microsoft Office Project Standard 2007. Assigned resources report status based on the actual work and the actual duration. You need to configure Project so that you can independently record the actual work and the actual duration. What should you do first?

You are tracking a project in Microsoft Office Project Standard 2007. Assigned resources report status based on the actual work and the actual duration. You need to configure Project so that you can independently record the actual work and the actual duration. What should you do first?

A.
Activate the Updating task status updates resource status option.

B.
Deactivate the Updating task status updates resource status option.

C.
Activate the Edits to total task % complete will be spread to the status date option.

D.
Deactivate the Edits to total task % complete will be spread to the status date option.



Leave a Reply 0

Your email address will not be published. Required fields are marked *