You need to put the tasks in the correct order

In Microsoft Office Project Standard 2007, you are creating a project plan from a list of serial tasks you have captured on paper. You have entered ten tasks in order and entered predecessors for all but the first task. You then notice that the eighth task should actually be between the fifth task and the sixth task. You need to put the tasks in the correct order. What should you do first?

In Microsoft Office Project Standard 2007, you are creating a project plan from a list of serial tasks you have captured on paper. You have entered ten tasks in order and entered predecessors for all but the first task. You then notice that the eighth task should actually be between the fifth task and the sixth task. You need to put the tasks in the correct order. What should you do first?

A.
Set the eighth task type to Fixed Duration.

B.
Enter 8 in the Successor field of the sixth task.

C.
Enter 6 in the Predecessor field of the eighth task.

D.
Activate the Autolink inserted or moved tasks option.



Leave a Reply 0

Your email address will not be published. Required fields are marked *