You need to display the actual cost of work performed (ACWP) for the last day of the previous update period

You are displaying a project schedule in Microsoft Office Project Standard 2007 in the Gantt Chart view. The Earned Value table is displayed. You need to display the actual cost of work performed (ACWP) for the last day of the previous update period. What should you do?

You are displaying a project schedule in Microsoft Office Project Standard 2007 in the Gantt Chart view. The Earned Value table is displayed. You need to display the actual cost of work performed (ACWP) for the last day of the previous update period. What should you do?

A.
Set the status date to the end date of the last update period.

B.
Set the current date to the end date of the last update period.

C.
Set the Earned Value method of all tasks to Physical % Complete.

D.
Set the Earned Value method of the project to Physical % Complete.