You are tracking a project in Microsoft Office Project Standard 2007. You update the project status to the current date. You need to identify which tasks are ahead of schedule, and which tasks are behind schedule. In the Gantt Chart view, what should you do?
A.
Use the PERT Analysis function.
B.
Use the Project Statistics function.
C.
Apply the progress line to the Gantt chart on the current date.
D.
Set the status date to the current date, and then filter the schedule to display only unfinished tasks.