You need to reschedule this remaining work accurately

You are managing a project schedule in Microsoft Office Project Standard 2007. You assign one resource to a 5-day task. After completing 4 days of work, he is called away on an emergency. The remaining 8 hours of work are due for completion tomorrow. The resource is unable to complete the task until next week: He will work 4 hours next Monday and 4 hours next Wednesday. You need to reschedule this remaining work accurately. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. You assign one resource to a 5-day task. After completing 4 days of work, he is called away on an emergency. The remaining 8 hours of work are due for completion tomorrow. The resource is unable to complete the task until next week: He will work 4 hours next Monday and 4 hours next Wednesday. You need to reschedule this remaining work accurately. What should you do?

A.
In the Task Usage view, set the remaining work for the task to 8 hours.

B.
In the Task Usage view, set the remaining duration for the task to 4 days.

C.
Set the timephased work to 4 hours each for Monday and Wednesday and 0 hours for the remaining days.

D.
Set the timephased actual work to 4 hours each for Monday and Wednesday and 0 hours for the remaining days.