You are starting a new project in Microsoft Office Project Standard 2007. As part of tracking this project, you will need to compare the original project schedule to the current project schedule in the default Tracking Gantt view. What should you do?
A.
Set a baseline.
B.
Set an interim plan.
C.
Add a progress line.
D.
Update the project tasks.