You are updating a project in Microsoft Office Project Standard 2007. Your company tracks travel costs as timephased data. You create a cost resource named Travel for travel expenses, and assign this resource to each phase of the project. You also create a budget resource named Travel Budget. Costs have not been incurred evenly over the duration of the tasks. With the project schedule displayed in the Task Usage view, you need to record travel costs as timephased data. What should you do?
A.
Update the actual cost for the Travel resource.
B.
Update the budget cost for the Travel Budget resource.
C.
Set the Cost accrual value for the Travel resource to Start.
D.
Set the Cost accrual value for the Travel resource to Finish.