You need to share the Gantt chart displaying the final three months of the project with a colleague who does not have access to Project

You are tracking a project of six months duration in Microsoft Office Project Standard 2007. You need to share the Gantt chart displaying the final three months of the project with a colleague who does not have access to Project. What should you do?

You are tracking a project of six months duration in Microsoft Office Project Standard 2007. You need to share the Gantt chart displaying the final three months of the project with a colleague who does not have access to Project. What should you do?

A.
Print the Gantt chart for the final three months of the project.

B.
Apply a filter to select only those tasks starting in the final three months of the project, and then print a custom Task report.

C.
Change the timescale on the Gantt chart to show quarters on the middle tier and months on the bottom tier. Then print a custom Task report.

D.
Configure the Gantt chart by using the Gantt Chart Wizard. Apply a filter to select only those tasks starting in the final three months of the project, and copy the resulting task list into an e-mail message.