You need to change the calendar options to set the default amount of work to 8 hours

In Microsoft Office Project Standard 2007, you create a new task in a project plan, and assign a resource to the task. The default task duration is 1 day, and the default amount of work is 7 hours. You need to change the calendar options to set the default amount of work to 8 hours. What should you do?

In Microsoft Office Project Standard 2007, you create a new task in a project plan, and assign a resource to the task. The default task duration is 1 day, and the default amount of work is 7 hours. You need to change the calendar options to set the default amount of work to 8 hours. What should you do?

A.
Set the hours per day to 8.

B.
Set the hours per week to 40.

C.
Set the days per month to 20.

D.
Set the default start time to 8:00 A M. and the default end time to 4:00 P.M.