What should you do?

In Microsoft Office Project Standard 2007, you create three tasks in a project plan by using the manual calculation mode. After you create the tasks, the Gantt chart displays the following image:
You need the Gantt chart to automatically display the tasks in sequence instead of in parallel. What should you do?

In Microsoft Office Project Standard 2007, you create three tasks in a project plan by using the manual calculation mode. After you create the tasks, the Gantt chart displays the following image:
You need the Gantt chart to automatically display the tasks in sequence instead of in parallel. What should you do?

A.
Display the Calendar view.

B.
Perform a project calculation.

C.
Set the project options so that Project automatically links inserted or moved tasks.

D.
Set the project options so that Project automatically adds new resources and tasks.