You need to ensure that the project scheduling calculations reflect a 7

Resources in your organization work a 7.5-hour day. In Microsoft Office Project Standard 2007, you create a new calendar based on the Standard calendar. You set the new calendar as the project calendar. You need to ensure that the project scheduling calculations reflect a 7.5-hour working day.
What should you do?

Resources in your organization work a 7.5-hour day. In Microsoft Office Project Standard 2007, you create a new calendar based on the Standard calendar. You set the new calendar as the project calendar. You need to ensure that the project scheduling calculations reflect a 7.5-hour working day.
What should you do?

A.
Modify the calendar view.

B.
Create an exception entry in the Standard calendar.

C.
Modify the default work week details in the new calendar.

D.
Set work hours as non-default working time in the Standard calendar.