You need to save the tasks, durations, views, and formatting of the current project for reuse

You are managing a project in Microsoft Office Project Standard 2007. You will be managing similar projects in the future, and plan to reuse information from the current project. You need to save the tasks, durations, views, and formatting of the current project for reuse. What should you do?

You are managing a project in Microsoft Office Project Standard 2007. You will be managing similar projects in the future, and plan to reuse information from the current project. You need to save the tasks, durations, views, and formatting of the current project for reuse. What should you do?

A.
Save the project as a template.

B.
Create a baseline of the project schedule.

C.
Copy the projects rows from the Gantt Chart view into another project file.

D.
Use the Organizer to transfer the information you want to save from your project into the Global.mpt file.