You need to have Project calculate the latest possible start date based on the fixed completion date

You are creating a project in Microsoft Office Project Standard 2007. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?

You are creating a project in Microsoft Office Project Standard 2007. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?

A.
Place a Finish No Later Than constraint on the completion milestone.

B.
Set the Schedule From option in the Project Information dialog box.

C.
Set the deadline date of the completion milestone to the fixed completion date.

D.
Select Tasks will always honor their constraint dates in the scheduling options.