You are managing the schedule for a multi-level project in Microsoft Office Project Standard 2007. The project is complete. There are a number of project milestones embedded at all levels of the project hierarchy. Your organization reports the names and finish dates of project milestones in a Microsoft Office Excel workbook. You need to export the project milestone data from the project schedule to an Excel workbook for the purposes of this report. What should you do?
A.
Save the project file as an Excel workbook by using the Project Excel Template option.
B.
Save the project file as an Excel workbook, using the existing top-level task mapping when prompted to do so.
C.
Save the project file as an Excel workbook, creating a new task-based map that includes the name and finish fields and the milestone filter, when prompted to do so.
D.
Filter the schedule to show only the milestones. Then save the project file as an Excel workbook, using the existing top-level task mapping when prompted to do so.