You need to align the project schedule data with the cost accounts

You are managing a project schedule in Microsoft Office Project Standard 2007. Your organization’s accounting system utilizes cost accounts to track expenses against revenue. You need to align the project schedule data with the cost accounts. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. Your organization’s accounting system utilizes cost accounts to track expenses against revenue. You need to align the project schedule data with the cost accounts. What should you do?

A.
Set up interim plans.

B.
Enter cost resources.

C.
Enter budget resources.

D.
Copy cost data from the Task Usage table into the accounting system.