You are creating a project schedule in Microsoft Office Project Standard 2007. Tasks A and B each have a projected duration of 10 days. You expect the actual duration of one or both tasks to change when work begins. You want Task B to start when Task A is 60 percent complete. You need to model these tasks in the project schedule by creating a dependency from Task A to Task B. Which type of dependency should you create?
A.
start-to-start, with a lag of 6 days
B.
finish-to-start, with a lag of C60%
C.
finish-to-start, with a lag of C40%
D.
finish-to-start, with a lag of C4 days