You are using Microsoft Office Project Standard 2007 to create a project schedule in which you will be tracking the critical path of a set of linked tasks. When you add new tasks, their start dates default to the project start date. You need to order the tasks on a timeline so that you can analyze the critical path. What should you do?
A.
Enter starting dates for the tasks.
B.
Assign resources, and then level them.
C.
Enter task IDs in the Predecessors column.
D.
Drag the tasks to their correct starting dates.