You need to model this task correctly in the project schedule

You are managing a project schedule in Microsoft Office Project Standard 2007. Payment for a task is due on the first day of next month. The task can start any time after you receive the payment. You need to model this task correctly in the project schedule. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. Payment for a task is due on the first day of next month. The task can start any time after you receive the payment. You need to model this task correctly in the project schedule. What should you do?

A.
Enter the task as a recurring task that starts on the first day of the month.

B.
Create a task with a Must Start On constraint for the first day of the next month.

C.
Create a task calendar for the task, with the first day of next month as a calendar exception.

D.
Set a finish-to-start dependency between this task and a placeholder task representing payment.